邦瑞通用型變頻器加減速時間參數(shù)設置步驟。下面我們就永邦生產的通用型變頻器如何進行加減速時間參數(shù)設置進行詳細說明
變頻器加速時間就是輸出頻率從0上升到最大頻率所需時間,減速時間是指從最大頻率下降到0所需時間。通常變頻器用頻率設定信號上升、下降來確定加減速時間。在電動機加速時須限制頻率設定的上升率以防止過電流,減速時則限制下降率以防止過電壓。
通用型變頻器加減速時間參數(shù)設置步驟
通用型變頻器加速時間設定要求:將加速電流限制在變頻器過電流容量以下,不使過流失速而引起變頻器跳閘。
通用型變頻器加減速時間參數(shù)設置步驟
通用型變頻器減速時間設定要點是:防止平滑電路電壓過大,不使再生過壓失速而使變頻器跳閘。通用型變頻器加減速時間可根據(jù)負載計算出來,但在調試中常采取按負載和經驗先設定較長加減速時間,通過起、停電動機觀察有無過電流、過電壓報警;然后將加減速設定時間逐漸縮短,以運轉中不發(fā)生報警為原則,重復操作幾次,便可確定出最佳加減速時間。
如果你還對通用型變頻器相關的信息不明白,可以咨詢我們技術人員
Steps for setting acceleration and deceleration time parameters of universal frequency converter
Steps for setting acceleration and deceleration time parameters of bongrui universal frequency converter. Below we on yongbang production of general inverter how to speed up and speed down the time parameter Settings for a detailed description
The acceleration time of frequency converter is the time needed for the output frequency to rise from 0 to the maximum frequency, and the deceleration time is the time needed for the decrease from the maximum frequency to 0. Usually frequency converter set signal rise, fall to determine acceleration and deceleration time. In the case of motor acceleration, the rise rate set by the frequency should be limited to prevent overcurrent, while in the case of deceleration, the fall rate should be limited to prevent overvoltage.
Steps for setting acceleration and deceleration time parameters of universal frequency converter
General frequency converter acceleration time setting requirements: the acceleration current is limited to the frequency converter overcurrent capacity, not to cause the frequency converter tripping.
Steps for setting acceleration and deceleration time parameters of universal frequency converter
The key points of setting the deceleration time of universal frequency converter are: to prevent the smooth circuit voltage from being too high, and not to make the regenerative overvoltage stall and make the frequency converter trip. The acceleration and deceleration time of general frequency converter can be calculated according to the load, but in the debugging, it is often adopted to set a long acceleration and deceleration time according to the load and experience, and observe whether there is over-current and over-voltage alarm through the starting and power failure motive. Then, the acceleration and deceleration setting time is gradually shortened, and the optimal acceleration and deceleration time can be determined by repeating the operation for several times in accordance with the principle that no alarm occurs in the operation.
If you still don't understand the information about universal frequency converter, please consult our technician